Appledore

Our Appledore site in Devon is playing a pivotal role in the UK’s Fleet Solid Support (FSS) programme, delivering critical bow sections for the Royal Fleet Auxiliary’s next-generation support ships.

Icono de Navantia en blanco

Under Navantia UK’s ownership, this historic shipyard is undergoing a major upgrade to align with the demands of modern naval construction.

Investment at Appledore forms part of a UK-wide regeneration strategy, enhancing the yard’s precision manufacturing capabilities with the latest digital tools and fabrication technologies.

A new state-of-the-art plasma cutter is replacing legacy equipment, increasing accuracy, speed and complexity in steel cutting — critical for delivering high-quality naval components on time and at scale.

To mark the kick off of our first defence contract, we are delighted to welcome HMS Quorn to Harland & Wolff (Appledore)

Our dockyard

Appledore dry dock

Main hall and dry dock

  • 2 x 60t main hoist and auxillary hoist of 10t
  • 7 x 10t gantry crane
  • Drydock 118m x 33.5m
  • Tides range from 3.4m – 6.8m
  • Height from dock bottom to underside of crane is 21m
  • Extensive 110V, 240V and 415V electrical supplies
Panel hall and bar preparation area

Panel hall and bar preparation area

  • 2 x 30t overhead crane
  • 8t vacuum lifting beam
  • 2 x 5t overhead crane
  • Transfer car systems
  • 12m working height to underside of crane
  • Automated gas cutting facilities up to 200mm

Burning hall and design offices

  • 3 x 10t overhead crane
  • 6t vacuum lighting beam
  • 2 x Techserv plasma cutter with extractor
  • Guillotine up to 12.5mm thick
  • Plate rollers up to 35mm thick
  • Press 640t pressure
  • Transfer car out onto steel stockyard
Minor assembly and cold frame bending shop

Minor assembly and cold frame bending shop

  • 1 x 20t and 1 x 10t overhead cranes
  • Plate rollers and brake press 20t pressure
  • Techserv plasma and gas cutting machine
Steel stockyard and shot blast plant

Steel stockyard and shot blast plant

  • 10t Goliath crane 62m span
  • Plate shot blast plant with automatic spray booth
  • Blast up to 3m wide x 0.5m section areas
Southside (3 storeys)

Southside (3 storeys)

  • Joinery and electrical workshop
  • Consumable stores
  • Maintenance shop
  • Project office space
Pipe fabrication area

Pipe fabrication area

  • 1 x 10t and 1 x 5t overhead cranes
  • Pipe racking system
  • Steel bandsaws and crop saws
  • 200mm automated pipe bender
  • Pipe shot blast unit
  • Welding benches and extraction
Fitting and machine shop

Fitting and machine shop

  • 5t overhead crane 5m height
  • Lathes, bandsaws and milling machines
Life Boat Slip

Life Boat Slip

  • 5t crane
  • 40m slip
  • 8t electric winch
  • Spray booth

Main Stores

  • Eaves height 6m
  • Racking (5 pallet high)
skills centre

Skills Centre

  • Single storey training centre

24-hour security

  • CCTV
  • Patrols

Newquay yard: commissioning & outfitting quay

  • Extensive quayside
  • Ample mooring bollards
Newquay yard 90m patent slip for vessels up to 300t

Newquay yard 90m patent slip for vessels up to 300t

  • Hydraulic winches
Newquay yard small boat facility

Newquay yard: commissioning & outfitting quay

  • New build / repair of boats up to 20m
  • 2 x 15t cranes